New stages of construction based on key milestones:
- The slab for the monolithic roof was cast at the 11th floor (+32.30)
- The monolithic diaphragms and columns were constructed at the 12th floor (+35.54)
- The slab for the monolithic roof was cast at the 12th floor (+35.54)
- Arrangement of internal blockwork has been completed through the 7th floor
- Arrangement of external blockwork has been completed on the 3rd and 4th floors